Annual exceedance probability (AEP)

Annual exceedance probability (AEP)

This is the probability of an event occurring in a year. It has been adopted by the Australian Bureau of Meteorology (BOM) and Australian Rainfall and Runoff (2019) as the preferred terminology for rainfall and flood magnitudes, superseding average recurrence intervals (ARIs).

A common standard for street drainage design will be an AEP of 20% or 10% as a minor storm, and 1% AEP as a major storm. The general threshold for flooding of properties is 1% AEP.

The BOM provides the following table showing the different terminologies:


Because it is difficult to apply AEPs for frequent events, the terminology of Exceedances per Year (EY) has been introduced. Note that 50% and 20% AEPs do not correspond directly to 2 and 5 year ARIs. Explanations are provided in the BOM site, at www.bom.gov.au/water/designRainfalls/ifd/ifd-faq.shtml#sec1q6.


    • Related Articles

    • Average recurrence interval (ARI)

      Also known as the return period, this is the mean time between occurrences of some event, such as a flood. It is used as the foundation of many design procedures based on acceptable frequencies of occurrence. For urban stormwater drainage design the ...
    • Rational method setup with 2016 I-F-D data

      Although it is not sanctioned by ARR 2019, it is likely that some designers will want to continue working with the rational method, maintaining the methods set out in the 1987 edition of ARR. This can be done in DRAINS with 2016 ...
    • Obtaining 2016 I-F-D Data

      The latest rainfall intensities and depths to be used in design and analysis procedures are obtained after completing the previous steps from the ARR Data Hub. If you want to obtain the 2016 IFDs separately to the ARR Data Hub click here. This ...
    • I-F-D (intensity-frequency-duration) relationships

      This is a three-way relationship that defines the statistical distribution of rainfalls expected to occur at a particular location. It is derived from statistical analysis of rainfall pluviometers or automatic raingauges, which record rainfalls ...
    • Rational Method

      Developed in the 19th century, the rational method is the most widely-used hydrological procedure for estimation of design flowrates. It employs the equation: Q = C.I.A / F where Q is a peak flowrate in m3/s or L/s, C is a dimensionless runoff ...